SBI PO 2018 Daily Quiz 01 Quantitative Aptitude “Data Interpretation”

Data Interpretation has always played a great role in selection for SBI PO, In Phase One exam also SBI has asked for Data Interpretation Questions in Quantitative Section . Data Interpretation Quiz SBI PO 2018  will help you learn important concepts in Data Interpretation. Attempt now to know your scores in DI Topic.


Question 1: The total expenditure is req
cutting the expenditure on administration equally in all the years. What will be the
percentage cut for 1989?
(a) 22.6

(b) 32.6
(c) 42.5
(d) 52.6

Question 2: If the length of line to be laid each year is in proportion to the estimated cost
for material and labour, what fraction of the total length is proposed to be completed by
the third year?
(a) 0.9
(b) 0.7
(c) 0.6
(d) 0.3

Question 3: What is the approximate ratio of the total cost of materials for all the
years bear to the total labour cost?
(a) 4 : 1
(b) 8 : 1
(c) 12:1
(d) 16 : 1

Question 4: If the cost of materials rises by 5% each year from 1990 onwards, by
how much will the estimated cost rise?
(a) Rs. 11.4 lakh
(b) Rs. 16.4 lakh
(c) Rs.21.4 lakh
(d) Rs.26.4 lakh

Question 5: It is found at the end of 1990, that the entire amount estimated for the
project has been spent. If for 1991, the actual amount spent was equal to that
which was estimated, by what percent (approximately) has the actual expenditure
exceeded the estimated expenditure?
(a) 39
(b) 29
(c) 19
(d) 9


Answer

Answer 1: c
Total expenditure = 52.1+267.5+196.4+209.5 = 725.5 lakhs.
If it has to be kept within 700 lakhs, the expenditures has to reduce by 25.5 laks.
So the expenditure reduced each year will be (25.5/4) = 6.375 lakhs.
Hence, percentage reduce for 1989 would be = (6.375/15) × 100 = 42.5%.

Answer 2: b
Costs of material and labor
1988 = 2.1
1989 = 95+70+15+25+25 = 230
1990 = 80+45+12+18+20 = 175
1991 = 75+60+16+21+18 = 190
Therefore proportion of these expenditures till 1990 = (2.1 + 230 + 175) / (2.1 + 230 +
175 + 190) = 0.6817.
This will also be the fraction of the total length of the line

Answer 3: b
Total material cost = (95+80+75+70+45+60+15+12+16+25+18+21) = 532
Total labour cost = (2.1+25+20+18) = 65.1
Therefore the ratio = 532 : 65.1 = 8 : 1 (approximately)

Answer 4: b
The costs that can be taken under the head “Materials” are : Cement, steel, Bricks and
Other building materials.
The estimated cost in 1990 = 80 + 45 + 12 + 18 = 155
The estimated cost in 1991 = 75 + 60 + 16 + 21 = 172
Cost of material rises by 5%,
Cost would rise by 0.05X (155 + 172) = Rs.16.35 lakhs.

Answer 5: b
Amount spent till 1990 = Rs.725.5 lakhs
Estimated Expenditure for 1991 = 209.5 lakhs.
Hence the increase in expenditure will be 209.5 on 725.5 = 28.87%.